Project Updates: Streets and Sidewalks

Posted on: March 25, 2025

[ARCHIVED] Transportation Project Updates - Week of March 24, 2025

Transportation Project Updates: Week of March 17, 2025


2024 Street Maintenance (TH Johnson/Bill Pickett, Lake, Mallard) 

  • March 25, 2025 - Working on getting contracts signed with Texas Road. Will not start construction until at least May. 

MLK Sidewalk 

  • March 25, 2025 – 60% Design Submittal to TXDOT this week. Working through some unknowns on property alignments relative to the planned sidewalk and drainage work needed as a part of the project. 

Transportation Alternatives Grants (FM 3349 Shared Use Path & Cross-Town Connector)

  • March 25, 2025 – Detailed application submittal window is April 16 – June 20. HDR is meeting with TXDOT first week of April to discuss feedback on project proposals. They are also working to get detailed submittals ready for the submittal dates.

2022 Street Maintenance (2nd, 4th, Mallard)

  • March 25, 2025 – Speed study results anticipated this week. Awaiting report from Geotech on warranty submissions for seal coat on 4th and 2nd. Anticipated this week.