Taylor Streets Project

2019 (FISCAL YEAR)
Infrastructure Bond Street & Utility Reconstruction Project

In Fiscal Year 2019, the City of Taylor approved $13.1 million in bond funds for infrastructure improvements. Part of the funds will be used to improve roads and drainage, replace water and wastewater lines, and repave driveways within the right-of-way.

The Infrastructure Bond Street and Utility Reconstruction Project’s nearing completion of the design phase for improvements along five city streets. The project will improve mobility and safety along these streets and within our community.

Project Overview

The Taylor Streets Project uses funds from the 2019 Infrastructure Bond to improve roads, address drainage issues, replace water and wastewater lines, and repave driveways within the City’s right-of-way.

Five streets will be reconstructed as part of the project:

  • W. Lake Drive
  • W. Third Street
  • N. Lynn Street
  • N. Robinson Street
  • Edmond Street

Contact Information

Question or issue
regarding construction?

Call: 512-517-8713

Email:
Clayton.Craig@hdrinc.com

Question about the
project in general?

General Inquiry: taylorstreetsproject@hdrinc.com

West Third Street Reconstruction

3rd Street Reconstruction and Road Closure Graphic

During construction, West Third Street will be closed to through traffic between Shaw Street and Davis Street. Signs to help you navigate during the construction will be placed along Second Street, Third Street and Fourth Street between Howard Street and Fowzer Street.

  • Road closure signs will indicate where the Third Street work begins and ends.
  • Detour signs will help navigate non-local traffic around the construction zone.

During construction, Third Street will remain open to local traffic, delivery and emergency services.

West Lake Drive Reconstruction

During construction, West Lake Drive will be closed to through traffic between Old Georgetown Road and FM 397. Signs to help you navigate during construction will be placed along FM 397, Meadow Lane, West Lake Drive, Second Street and Old Georgetown Road.

  • Road closure signs will indicate where the Lake Street road closure begins and ends.
  • Detour signs will help navigate non-local traffic around the construction zone.
  • Traffic cones will also be placed along FM 397 due to the Lake Street turn lanes being closed.

Lake Street will remain open to local traffic and service access during construction.

West Lake Drive Road Reconstruction and Closure Graphic
West Lake Drive Construction Update August 4

Lynn Street Reconstruction

North Lynn Street Detour Reconstruction Map

During construction, North Lynn Street will be closed to through traffic between Davis Street and West Lake Drive. Detour signs will help navigate non-local traffic around the construction zones. The street will remain open to local traffic and services access during construction.